All Projects:
Limit of Clearing: The limit of clearing for the entire project, or each phase if the project is phased, shall be staked under the supervision of a registered Professional Engineer or a Registered Professional Land Surveyor and approved by the Commission and/or its Agent prior to any clearing activities.
Erosion Control Barrier: The Commission and/or its Agent must inspect and approve the installation of the erosion control barrier prior to commencement of work.
Foundations: All foundations or other structures shall be staked under the supervision a registered Professional Engineer or a Registered Professional Land Surveyor prior to installation as required by the Order of Conditions and approved by the Commission and/or its Agent prior to installation.
Certificate of Compliance: The Commission and/or its Agent must inspect and approve the project upon completion of work and stabilization of site.
Residential Subdivisions/Commercial & Industrial Development:
Erosion Control Barrier: The Commission and/or its Agent must inspect and approve the installation of the erosion control barrier prior to commencement of work.
Limit of Clearing: The limit of clearing for the entire project, or each phase if the project is phased, shall be staked under the supervision of a registered Professional Engineer or a registered Professional Land Surveyor and approved by the Commission and/or its Agent prior to any clearing activities.
Roadway and Stormwater Mangement Facilities: The roadway and stormwater management facilities shall be staked out by a registered engineer and approved by the Commission and/or its Agent prior to commencement of work.
Foundations: All foundations or other structures shall be staked under the supervision of a registered Professional Engineer or a registered Professional Land Surveyor prior to installation as required by the Order of Conditions and approved by the Commission and/or its Agent prior to installation.
Certified Plot Plan: When required by the Order of Conditions, a certified plot plan prepared by a registered Professional Land Surveyor shall be submitted and approved by the Commission and/or its Agent prior to erection of the structure.
Certificate of Compliance: The Commission and/or its Agent must inspect and approve the project upon completion of work and stabilization of site. At a minimum, a Partial Certificate of Compliance should be requested before receiving an Occupancy Permit.
|